Project description
The “Daniel del Olmo” bridge is in the city of Valladolid, at the entrance to the Argales industrial estate. Its 18 m wide deck has 11 simply supported spans carried on precast pre-tensioned joists with a top slab cast in situ. All spans are 9 m long on 46 joists 0.40 m deep, except the central one over the railway, which spans 18 m on 36 beams 0.72 m deep. Loads are transferred to the substructure through lead bearings wedged with steel plates, which take up the steep longitudinal gradient.
There were no expansion devices at the deck joints between spans, nor any deck drainage. The proportion of heavy traffic is high, as would be expected given the bridge’s location. It is also exposed to a harsh climate with frequent freeze-thaw cycles and to an industrial environment.
The work was divided into three phases:
PHASE I.- Assessment of the structure. A special inspection was carried out (damage survey and complementary tests), together with an analysis of the load-bearing capacity of the structure. The most alarming damage was in the pier crossheads, which showed alarming loss of steel section. The beam seats were also in a ruinous state.
PHASE II.- Rehabilitation project for the bridge. Among other works, the crossheads were strengthened with resin-bonded carbon-fibre laminates, the beams that were not in a ruinous state were repaired, and those that could not be recovered were replaced or strengthened with carbon-fibre laminates. The bearings were also changed, and solid concrete crossbeams were built, resting on new elastomeric bearings. On the deck, the surfacing, parapets and kerbs were replaced, and drainage and expansion joints were installed.
PHASE III.- Technical assistance during the rehabilitation works described above.